Tuesday, 12 May 2009


The concrete sections have finally been installed. There was a problem with the logistics of loading and unloading which resulted in the lifting gear having to be returned to site for an additional half a day and therefore at additional expense. Hopefully the last unplanned for incident. The forms look good, however the moulding process has resulted in a colour variation that is not desired. It seems the preferred fabric used for the casting was used up half way through their build and an alternative, whilst appearing similar, has for some reason create a variation in the colour. It seems that we will have to paint the concrete in a special wash, designed for this very problem..so what I said about no more unforseen problems, lets hope tomorrow goes to plan.
The result of the delayed installation of the concrete is a day's delay to the living wall panels that fiit to the vertical walls between the concrete sections. They are expected tomorrow and should soften up the space

No comments:

Post a Comment